Construction start: Macdonald-Stewart - Upgrade Fire Suppression System LOT 1A
Please be advised that 㽶Ƶ has mandated Gicleurs Moderne Inc. to carry out the following project: 24-001 Macdonald Stewart - Upgrade Fire Suppression System LOT 1A (work in 3 laboratories).
ٱپDz:Installation of the main sprinkler line in the ceiling of three teaching laboratories located in the basement level of Macdonald-Stewart Building #446.
Construction start date: June 20, 2024
Planned construction end date: August 9, 2024
Work schedule: Monday to Friday 6 a.m. to 3 p.m. Any additional hours will be coordinated.
Project Manager: Biagio D’Onofrio - biagio.donofrio [at] mcgill.ca
Assistant Project Manager: Claudia Carpanzano - claudia.carpanzano [at] mcgill.ca
Contact for building users: Youssef Chebli, Ph.D. - youssef.chebli [at] mcgill.ca
Scope of work:
- Installation of a 6” main sprinkler pipe in the ceiling of teaching labs MSB-013, MSB-031 and MSB-027, and part of B-HALL1 and B-HALL2.
Impact & mitigation:
- Construction will be limited to interior spaces only: MSB-013, MSB-031, MSB-027, B-HALL1 and B-HALL2. Minor modifications to circulation within the basement level of Macdonald-Stewart will be required.
- There will be some medium and high levels of noise at times.
- Any access to spaces outside the construction zone will be coordinated in advance with the building director and the building occupants.
No service shutdowns will be required.