Construction Starts: Raymond – JELF Dastmalchi (Lot 2)

Picture depicting the front view of Raymond building
Published: 23 December 2024

Please be advised that Ï㽶ÊÓƵ has mandated XO Construction Inc. to carry out the following project: 21-002 Raymond (Macdonald Campus) – JELF Dastmalchi (Lot 2)

¶Ù±ð²õ³¦°ù¾±±è³Ù¾±´Ç²Ô:ÌýRenovation of room R1-038.

Construction start date: January 2025

Planned construction end date: July 2025

Work schedule: Monday to Friday, 6 a.m. to 3 p.m.

Project Manager: mark.ouimet [at] mcgill.ca (Mark Ouimet)

Assistant Project Manager: mark.grzywacz [at] mcgill.ca (Mark Grzywacz)

Contact for building users:

Building Director - youssef.chebli [at] mcgill.ca (Youssef Chebli)

-------------------------------------------------------------------------------------------------------

Scope of work:

Lot 2 of this project consists of renovating the lab and upgrades to mechanical and electrical distribution in lab R1-038.

Minor electromechanical work will take place in the adjacent hallway (1-HALL4 and 1-HALL3) and in room R1 018B.

Impact & mitigation:

  • Exterior portion:
  • An exterior zone in the Raymond courtyard will be fenced off and used as a storage space, container location and an alternative access point to the site.
  • Service shutdowns:
  • Minor electrical and ventilation service shutdowns will be required. Occupants and users of affected buildings and rooms will be informed in advance.
  • A temporary fire alarm bypass will be required within the affected zone.
  • During construction, access to Raymond’s electromechanical rooms will be required for related work. Such construction work will be coordinated in advance with the building director, adjacent projects and the building occupants.

Safety considerations:

The project includes demolition work that will disrupt materials containing silica and asbestos. All applicable safety protocols will be put in place. The safety protocols include dust-containment methods such as setting up enclosures to isolate the work area and putting it under negative pressure, decontamination showers, as well as using specialized vacuuming equipment. It will also include cleaning and regular inspections.